Residential Tower Scheduling

Aranya Heights — Tower B (G+12, 48 Units). 18 tasks, 13 contractor crews, RERA-compliant deadline. See how Solver optimizes and adapts in real time.

18
Tasks
13
Contractor Crews
99
Total Work Weeks
63
Project Duration (wk)
RERA Status
Baseline Schedule
63 weeks
Optimizing schedule...
Evaluating 0 configurations
RERA Deadline
8 weeks saved

Optimization Results

Schedule improvements found by SimplexArc Solver

Baseline 63 weeks
Optimized 55 weeks
Project Duration
Baseline 0 weeks
Saved 8 weeks
Time Saved
Baseline
Improvement 12.7%
Schedule Improvement
RERA Deadline 65 weeks
Margin 10 weeks
RERA Safety Buffer

Built for Indian Real Estate

RERA deadlines. Monsoon disruptions. Multi-tower projects. SimplexArc Solver keeps your schedules optimized as reality changes — in seconds, not days.